|
|
Installation notes |
| These
installation notes are for general guidance only in fixing Onduline
material. For special applications or variations in roof form,
please contact Onduline's technical department for assistance. |
|
Caution |
| Covering
existing fragile corrugated roofs is a specialist operation. All
work should be carried out with due regard to all Health & Safety
regulations: this is of particular importance when dealing with
fibre-cement materials possibly containing asbestos. Under no
circumstances should blue and brown asbestos be oversheeted and on
any roof containing old asbestos , consult your Environmental Health
Officer for guidance and follow relevant site handling requirements.
It is advisable not to clean corrugated fibre-cement sheets. Treat
them with a dilute PVA adhesive coating to consolidate the internal
and external surfaces prior to fixing. Finally lay Ondutiss roofing
membrane onto main support battens to seal roof. Building
regulations should be adhered to and in some instances planning
approval may be required. |
|
|
Preparation |
| A
thorough inspection of the existing roof structure should be
undertaken, any deterioration of the existing roof should be
rectified and the structure checked as to its suitability for
oversheeting procedures. A revue of the original roof design should
be made to check that sufficient ventilation and insulation is
provided, and if necessary alterations incorporated in the Onduline
Oversheeting System refurbishment. |
|
|
Fire resistance. |
| All
statutory requirements should be adhered to in accordance with
relevant British Standards and Code of Practice. Consult Onduline's
technical department if specific project information is required. |
|
|
Fixing procedure |
| Fixing
the main support battens |
| Select
the correct section of timber to suit existing sheet corrugation
size in accordance with timber schedule, and fix from eaves to ridge
through the existing roof covering in accordance with fixing
schedule. |
| NOTE:
|
- Allowance should be made for
additional space required for provision of insulation.
- Fragile roofs will require
pre-drilling.
- All battens must be treated.
- If asbestos is expected in the
roof, overlay main support battens with Ondutiss membrane.
|
|
Fixing Onduline
support battens |
| Overlay
and fix the main battens with the Onduline support battens, verge to
verge, at 450 or 600mm centres in accordance with the Onduline
timber fixing schedule. |
| Note.
Eaves tray and ridge components require additional support battens. |
|
|
Fixing Onduline sheets |
| Care
should be taken rto ensure that the fixing penetrate the batten
centrally |
|
| Insulation
option |
| Onduliss
vapour check membrane is laid up the roof from verge to verge over
the main support battens with 100mm side and end laps. The Ondutiss
is overlaid with the Onduline support battens. The insulation is
laid between the support battens. The Onduline sheet can then be
fixed. |
| Note.
Ventilation must be provided below the Onduline sheet. |