When butting lengths of trim together, ensure that a section
of foam seal is positioned between the joint. The top edge
of the trim should be level or just below the surface of the
roof deck waterproofing. Finely fix the joint clips by
applying a bead of silicone to one side of the joint, then
hook the clip under the bottom edge of the trim and snap the
top edge over the top.
Quicktrim
Check Kerb
Cut the Check kerb to
required lengths allowing a 3mm expansion gap at all joints.
Tidy up cut ends with fine sandpaper. Press the kerbs down
firmly compressing the foam seal on to the membrane surface,
then gently hammer the fixing pins through the slotted
fixing points. Pre-drill additional slotted fixing holes to
suit any cut lengths. When butting lengths of trim together,
ensure that a section of foam seal is positioned between the
joint. Finely fix
joint clips by applying a bead of silicone to one side of
the joint, then hook the clip under the bottom edge of the
trim and snap the top edge over the top (see Fig. 2).
Upstands
The underlay will already be
placed up the adjacent wall to about 50mm
height from the the
roof surface. The extra strip of Top Sheet should be applied
to the wall and brought down on to the slate surface deck to
cover the upstanding section. The detailing strip and deck
should be bonded together with Coldseal Lap Mastic. |